The Petaluma Valley Groundwater Sustainability Agency (GSA), in partnership with the City of Petaluma, conducted a pilot test in 2025 at an existing well near Del Oro Park to evaluate the feasibility of adding, storing and recovering drinking water in the underground aquifer. This process is known as Aquifer Storage and Recovery (ASR), which you can learn more about here.

The pilot was designed to determine if this location is viable for ASR to diversify and sustainably manage our local water supply in the future—especially in preparation for droughts, emergencies, and peak demand periods. The pilot consisted of temporarily equipping an existing well with ASR capabilities to store water from Sonoma Water’s drinking water supply into the underground aquifer system. The well, owned by the City of Petaluma, was constructed in 2003 but has been out of service due to high levels of naturally occurring minerals. This pilot test was designed to determine if adding drinking water into this well would dilute the mineral concentrations. The pilot aimed to store and recover approximately 2.2 million gallons of drinking water through three cycles.

Project Location

The pilot test was conducted at the Del Oro well, which is located at the southeastern corner of Del Oro Park near the intersection of Adobe Creek and Sartori Drive in Petaluma.

Project Timeline

  1. March – June 2025: Planning and regulatory permit review and approval
  2. June – August 2025: Two monitoring wells installed surrounding the Del Oro well to monitor aquifer response to storing and recovering water
  3. August 2025: ASR pilot begins
  4. August – December 2025: Three ASR cycles completed while collecting groundwater and water quality monitoring data
  5. December 2025 – March 2026: Data analysis and final reporting

Project Results

Across the three cycles of adding, storing, and recovering, a total of 779,300 gallons of potable water were added to the groundwater aquifer, considerably less than the target of 2.2 million gallons. The results indicate a limited capacity of the aquifer to accept high volumes of water at this location. In addition, the depth to groundwater at this location is relatively shallow, which limited the available underground storage space above the aquifer. The depth to groundwater was approximately 17 feet below ground surface prior to the ASR pilot test, and pilot operations raised groundwater levels to 7 feet below ground surface.

During the pilot, the overall water quality characteristics at the Del Oro Well changed as expected. Stored water was unsurprisingly a mixture of native groundwater and the added drinking water. Following recovery, the water  shifted back to the characteristics of the native groundwater. Target mineral levels (such as arsenic) did not decrease as hoped, and instead increased during recovery pumping. It is likely that the introduction of the drinking water created conditions that released arsenic from the saturated soils. Arsenic concentrations were lower during the third ASR cycle as compared to the first two cycles, which suggests aquifer conditioning is occurring and that more recharge cycles could reduce arsenic levels to meet drinking water criteria.

The consultant team recommends further ASR pilot testing at the Del Oro well to determine if water quality stabilizes over time and that other sites be considered within the City for ASR development.

Read the full technical report here.

Project Funding

The ASR pilot test was funded through a grant issued from the California Department of Water Resources (DWR). Results from the pilot test provide valuable information for the Petaluma Valley GSA and the City of Petaluma to consider ASR and other regional water banking opportunities the Petaluma Valley groundwater subbasin.

 